The digging work of the DMRC on the Adohini-Andheriamore stretch
requires Twenty-four men to complete the work in sixteen days. As a part of the task if DMRC were to hire Thirty-two women, they can complete the same work in twenty-four days. Sixteen men and sixteen women started working and worked for twelve days. Due to time bound schedule the work had to be completed in remaining 2 days, for which how many more men are to be employed?

Articles

daily news digest:03 december 2020

Explained: international day of persons with disabilitiesthe theme for international day of

Read more..

topic of the day

Economy important concepts-gross domestic product & gross value added what is gdp? gdp

Read more..

this day in history

3 - december – 1884: dr rajendra prasad, first president of india, was born in jeradei

Read more..

places in news

Suriname it is a country on the northeastern atlantic coast of south america. it is bordered

Read more..

Provide comments

COPYRIGHT NOTICE: Please do not copy and paste content from here. This content is either purchased or provided by experts. Please report copyright violation of genuine owner of content to [info at onlinetyari.com]. It will be removed within 24 hours after ownership check.

FAIR USE POLICY: You can show our questions on blogs/facebook pages/Any web page/Apps on condition of putting [Source:OnlineTyari.com] below the question.